⚡ KENTUCKY POWER PROPOSES $2.85 BILLION NATURAL GAS PLANT IN LOUISA TO SUPPORT DATA CENTER
Appalachia Insider · November 17, 2026
Kentucky Power is seeking state approval to construct a new natural gas power plant in Lawrence County to support an $8.5 billion data center development in northeastern Kentucky.
The proposed facility would be built at the existing Big Sandy power plant site near Louisa, generating approximately 760 megawatts of electricity at an estimated cost of $2.85 billion.
The project is tied to TeraWulf’s planned Muskie Data Campus in Boyd and Greenup counties, which could require up to 1,000 megawatts of electricity by 2029.
Kentucky Power is also requesting approval for a new transmission substation in Boyd County and temporary electricity purchases from facilities in other states.
The new power plant is projected to begin operating in 2031, pending regulatory approval.
The proposals are currently under review by the Kentucky Public Service Commission.
Source: Mountain Top Media
#AppalachiaInsider #KentuckyPower #LawrenceCounty #LouisaKY #EconomicDevelopment #EasternKentucky